Full Bathroom Refurbishment

Brighton PlumberBrighton and Hove Plumber - Highly recomended

Based on small bathroom - Tiling just around the bath and simple lino flooring.

A full bathroom refurbishment can take from five to seven days. The installation starts with taking the whole bathroom back to bare walls and starting from scratch. Any plastering that needs doing will be completed first so that the tiles have a flat firm wall to attach to. Sanding down of window frame and any other surface to be painted later is completed next.
Any changes to the pipe work are then completed (plumber’s first fix). Possibly channeled into the wall or repositioned. A frame has to be made next for the bath, the bath then checked in place and marked out for tiling. Any boxing in will be done now (sometimes it is nicer to box pipe work in giving you a low level shelf). The tiling around the bath can be done now. The bath then brought back then secured to the floor, wall and bath frame to make it solid.
Now the floor, if there’s room the grouting of the tiles can be done the same day. Toilet and basin can now be fitted as the floor is complete (plumber’s second fix). Tiles around the basin can be completed now if needed. Last thing - the painting, sealant and shower door if necessary.

Day one:  Gut the bathroom (leaving toilet) and plaster where necessary.
Also if time (and space) unpack and dress the bath, toilet and basin.

Day two:  Marking out, pipe work, bath frame and boxing in.

Day three:   Tiling then fitting / securing the bath.

Day four:   Grouting and floor work. Some of day five can be done. Sometimes the whole bathroom can be finished on day four if there was not much plastering, boxing in or channeling pipes in the wall.

Day five:  Fit basin, new toilet, shower door (on side of bath) and decorate - Finished.

 

FULL BATHROOM REFURBISHMENT - With separate shower, no bath

Based on small bathroom - Tiling just around the shower area and simple lino

Basically a similar quote as with a bath though a shower will take approximately two days longer as more tiling to be done and the shower trap has to be positioned perfectly to allow the correct flow of waste water; access to the trap (for maintenance) has to be fitted and the shower tray might have to be positioned on cement if it is ceramic.

Bathroom Suite and tiles – Customer to chose, email me suite description to check for ease of installation and compatibility.

A full bathroom refurbishment can take up to seven days. The installation starts with taking the whole bathroom back to bare walls and starting from scratch. Any plastering that needs doing will be completed first so that the tiles have a flat firm wall to attach to. Sanding down of window frame and any other surface to be painted later is completed next.
Any changes to the pipe work are then completed (plumber’s first fix). Possibly channeled into the wall or repositioned. A frame has to be made next for the shower tray. Any boxing in will be done now; sometimes it is nicer to box pipe work in giving you a low level shelf. With the shower tray set up, the tiling can be done. The shower tray can then be secured to the frame to make it solid.
Now the floor, if there’s room the grouting of the tiles can be done the same day. Toilet and basin can now be fitted as the floor is complete (plumber’s second fix). Tiles around the basin can be completed now if needed. Last thing - the painting, sealant and shower door if necessary.

Day one:  Gut the bathroom (leaving toilet) and plaster where necessary.
Also if time (and space) unpack and dress the shower tray, toilet and basin.

Day two:  Marking out, pipe work, shower tray frame and boxing in.

Day three:   Tiling

Day four:  Fitting / securing the shower tray, trap and waste pipe.

Day five:   Grouting and floor work.

Day six:  Fit basin, new toilet, shower doors.

Day seven:  Sealant and painting - Finished.

Job done! Highly professional plumber for you in Brighton and Hove....

Practical Plumbing Solutions

13A St Lukes Rd

Brighton

East Sussex

BN2 9ZD

Mr Gregory Milne-Redhead

Perfection

Highly trained partners

Excellent workmanship

Quality services

Just check out my pet cat...

 

Practical Plumbing Solutions

Call me: 07876654005

Tap Specialist

Bathroom Specialist

Kitchen Specialist

Gas Safe plumber available